Thermal Blanket Insulation

Steam Turbine Insulation Case Study: 314 Custom Removable Insulation Blankets for Alstom and Siemens Steam Turbines

Delivering a Complex Steam Turbine Insulation Project Within a Critical Shutdown Window

Steam turbine insulation projects are among the most demanding applications in industrial insulation. High operating temperatures, complex equipment geometry, restricted access, multiple contractors working simultaneously, and tight shutdown schedules leave little room for error.

TAS Blanket Insulation recently completed a turnkey insulation project involving two major steam turbines—one Alstom unit and one Siemens unit—along with their associated steam piping, valves, flanges, and fittings. The project comprised 314 individually engineered removable-reusable insulation blankets, all custom designed, manufactured, and installed to meet the customer's strict shutdown schedule. From the completion of site measurements to finished manufacturing, the entire engineering and production process took just two weeks.

Despite the differences in manufacturer geometries, the complexity of the equipment, and the challenging site conditions, every blanket fitted precisely during installation, allowing the project to be completed successfully before turbine commissioning.

 

Project at a Glance

Equipment:

  • One Alstom steam turbine
  • One Siemens steam turbine
  • Associated steam piping, valves, flanges, and fittings

Scope & Insulation System:

  • 314 custom removable-reusable insulation blankets
  • Two-layer construction with a total insulation thickness of 100 mm

Materials:

  • High-temperature silica insulation
  • Reinforced stainless steel mesh construction

Services Provided:

  • Removal of deteriorated insulation blankets
  • Detailed site measurements & CAD engineering
  • Custom manufacturing & sequential installation
  • On-site mobile manufacturing support

Engineering & Manufacturing Turnaround:

  • Two weeks from completed measurements

 

Why Steam Turbine Insulation Matters

Steam turbines operate with high-temperature, high-pressure steam. Depending on operating conditions, external surface temperatures can exceed 500°C, creating a significant burn hazard for personnel and continuously radiating valuable energy into the surrounding environment.

A properly engineered steam turbine insulation system provides several critical benefits:

  • Thermal Efficiency: Dramatically reduced heat loss and improved energy efficiency.
  • Personnel Safety: Lower external surface temperatures and reduced radiant heat within the plant environment.
  • Operational Agility: Safer, faster maintenance turnarounds through a predictable removable insulation design.

Unlike conventional pipework, both Alstom and Siemens turbines feature highly irregular geometries with numerous inspection covers, bolted casings, auxiliary piping, and support structures. Because these components require regular maintenance, custom removable insulation blankets are the preferred solution over conventional rigid insulation.

 

The Challenge: Zero Margin for Error

This project required complete thermal coverage across two distinct turbine geometries while maintaining future maintenance access. The insulation system incorporated two layers with a combined thickness of 100 mm, providing high thermal performance while remaining manageable for site crews.

The project presented several technical challenges:

  • A highly compressed shutdown schedule with only two weeks allocated for CAD engineering and manufacturing.
  • Managing two completely different OEM design styles simultaneously.
  • Extremely limited installation space beneath and around the turbines.
  • A precise fit required on the first try, with no opportunity for field corrections or remake items after startup.

 

Removing the Existing Insulation

Before the new insulation system could be measured and engineered, the old, deteriorated insulation had to be stripped. It was in very poor condition—damaged, compressed, and completely degraded after years of service, which significantly reduced both thermal performance and mechanical integrity.

Removing this deteriorated material required approximately two to three days before accurate measurements could even begin. Its condition reinforced a vital engineering lesson: durability matters. Because steam turbine insulation blankets are repeatedly removed and reinstalled during major overhauls, they must possess exceptional mechanical strength to prevent tearing or losing their shape over time.

Steam turbine casing and connected piping requiring custom insulation engineering

 

Working During an Active Overhaul

The project became even more demanding because measurements had to be carried out while the turbine overhaul was already underway. As our team prepared the equipment for measurement, the turbine repair contractor had already begun dismantling the units.

With several contractors requiring access to the equipment at different stages, constant coordination between plant maintenance, turbine specialists, and the TAS project team was essential to ensure measurements were completed without delaying the mechanical overhaul.

 

Steam turbine measured while overhaul activities are in progress

 

 

Detailed Site Measurements and CAD Engineering

Once the turbines and surrounding equipment were fully accessible, detailed measurements were carried out across turbine casings, steam piping, valves, flanges, branch connections, and complex transition areas. Based on these data points, every one of the 314 insulation blankets was individually engineered using CAD to match the specific profiles of the Alstom and Siemens machinery.

Old damaged insulation removed from a steam turbine before site measurements

 

[Site Measurement] ➔ [CAD Engineering & Segmentation] ➔ [Precision Manufacturing] ➔ [Sequential Installation]

The insulation system was strategically divided into logical blanket sections so that individual areas could be removed during future maintenance without unnecessarily disturbing the surrounding insulation.

Blanket size and weight limitations were carefully considered. Large insulation sections can become unwieldy and unsafe to handle, increasing installation times and the risk of damage. Each blanket was designed to achieve the optimum balance between thermal performance, mechanical strength, and practical handling, allowing maintenance personnel to safely manage individual sections without specialized lifting equipment.

 

 

 

High-Temperature Materials and Reinforced Construction

The insulation system was manufactured using high-temperature silica insulation materials, specifically selected for the demanding operating temperatures encountered in steam turbine applications. To maximize long-term durability, every blanket incorporated a reinforced stainless steel construction.

This reinforcement helps the blankets:

  • Maintain their exact shape over many maintenance cycles.
  • Resist mechanical damage during handling.
  • Withstand repeated removal and reinstallation, representing a massive lifespan improvement over the legacy insulation system.

 

 

Manufacturing and Difficult Installation Conditions

Following the site measurements, the TAS project management, design, and production teams worked around the clock to execute CAD engineering, blanket segmentation, material cutting, sewing, stainless steel reinforcement, and strict quality control within the two-week window. With 314 unique blankets, accurate identification and clear labeling were essential for an organized deployment.

Installation proved to be one of the most challenging phases of the project. The space beneath the turbines was extremely restricted, leaving very limited room for installers to position the blankets and secure the fastening systems.

The two-layer, 100 mm insulation system added further complexity; each inner-layer blanket had to be securely positioned before the corresponding outer-layer section could be aligned around the turbine casings and fittings. Because the turbines were scheduled for immediate commissioning, there was zero opportunity for field modifications after startup.

To mitigate this risk completely, TAS deployed a fully equipped mobile manufacturing station on-site via our service van. This allowed our team to handle immediate, precision adjustments on-site if required, guaranteeing the tight startup deadline would be met regardless of unforeseen site challenges.

The Result: Thanks to this rigorous preparation, the entire system integrated flawlessly. All 314 custom removable insulation blankets were installed successfully within the restricted window, confirming the absolute accuracy of the initial site measurements, CAD engineering, and proactive project planning.

 


Project Takeaways: Why Precision Matters

A removable insulation blanket must do much more than simply fit around equipment. For complex machinery like Alstom and Siemens steam turbines, precise engineering significantly reduces plant downtime over the insulation system's lifetime. Precise segmentation, clear identification, and manageable blanket sizes allow maintenance teams to isolate and remove only the sections required for servicing, getting the equipment back online quickly.

The Upgraded System Delivers:

  • Proven Performance: Complete thermal coverage capable of handling sustained temperatures above 500°C.
  • Longevity: Structural reinforcement that prevents sagging, tearing, and degradation during future maintenance shutdowns.
  • Turnkey Execution: Seamless delivery from initial teardown to final QA within a critical, multi-contractor shutdown window.

Successful steam turbine insulation requires far more than manufacturing high-quality materials; it demands experienced project management that integrates smoothly with active mechanical overhauls where every hour counts.

 

 

Planning a Steam Turbine Overhaul or Shutdown?

A successful steam turbine insulation project requires specialized engineering that can handle complex casing geometries, intense thermal demands, and aggressive shutdown schedules.

Whether you operate Alstom, Siemens, or other major OEM steam turbines, TAS Blanket Insulation provides complete turnkey removable insulation solutions—from initial teardown and precision CAD design to custom manufacturing and fast on-site installation.

Don't let insulation delays impact your commissioning timeline. Contact TAS Blanket Insulation today to discuss your upcoming turbine overhaul and ensure your next shutdown stays on schedule.

 


Steam Turbine Insulation Case Study: 314 Custom Removable Insulation Blankets for Alstom and Siemens Steam Turbines

 

Learn more about how removable and reusable insulation can improve safety and efficiency across your steam system.

Learn more about how precision-engineered blanket insulation improves thermal performance and maintenance efficiency for complex industrial equipment in our related technical articles.

If we can assist you, please contact us or request a free TAS Energy Audit today.

Steam Turbine Insulation Case Study: 314 Custom Removable Insulation Blankets for Alstom and Siemens Steam Turbines

 

 

 

“Quality, Sustainability, Energy Efficiency”

Latest Articles

As part of our service, we offer a Free Energy Audit...

...providing our clients with a clear insight into potential cost savings and the fast return on investment of our insulation solutions.

As part of our service, we offer
a Free Energy Audit...

...providing our clients with a clear insight into potential cost savings and the fast return on investment of our insulation solutions.
Book your
 free energy
 survey today!
ORDER
Thermal imaging and energy survey used to assess heat loss in industrial systems

Our Achievements in Numbers

0
Projects Completed
successfully
0
million € savings
achieved
0

tonS of CO2 Emissions
reduced

Delivering Sustainability with Quick Payback
15 years expected lifetime with tas thermal blanket insulation15 years lifetime with TAS Thermal Blanket Insulation

Request a quote  now!  

Request
a quote 
now!  

Removable reusable blanket insulation solutions for thermal, acoustic, and safety applications
Removable reusable blanket insulation solutions for thermal, acoustic, and safety applications
Request a brochure or a sample
Enter your email
or postal address & we will send it to you!
Prospectus

Our Customers

Our Customers

TAS BLANKET INSULATION KFT.
4110 Hungary Biharkeresztes, Bojti st. 1.
+36 54 501 046
info@tasblanketinsulation.eu